15. NIT NO. 90 CAO C SC-2022,
Dated 21-11-2022 Name of work SCR
Construction Organization Nadikudi Srikalahasti
New BG Line Project Major bridge
locations from CH 74700M to CH 155000M
between existing Gundlakamma (Except)
and proposed Kanigiri (Inclusive) stations
Remaining work of construction of major bridges
including earth work, protective work and
miscellaneous works in formation for
bridge approaches at Bij no. 103, (ii)
10×12.20m PSC girder on open
foundation as per Ch. 76982M AT BRIDGE NO.
105. (iii) 2×12 20m PSC Girder (Super
Structure) as per CH 96850M at Bridge No.
144, (iv) 1×18 30m Skew PSC ‘U’ Girder
(Super Structure) as per Ch. 98424 at
M.BRIDGE NO. 148, (V) 1×24.00m
Composite Girder (ROB) on Open
Foundation as per Ch. Bridge no.115000m.
173A, (vi) On Pile Foundation 4×12. 2m
PSC girder as per Ch. 120575 at M.BRIDGE
NO. 179, (vii) 2×12 2m PSC slab on
open foundation (as per RUB CH 121830m
at Bridge No. 180. | (viii) 2×9.15m PSC
slab on open foundation (as per RUB
CH.
122681m at Bridge No. 181 , (ix)
3×18.3m PSC girder on open foundation as per
Ch.141350m at Bridge No.204, (x) 2×12.2m
PSC slab (RUB) on open foundation as
per Ch.149915m at Bridge No.210, ( xi)
Bridge No. 216 on open foundation 122. 2m
PSC
girder ( as per rub ch. 154754
) m. Estimated cost Rs. 104,46, 28,
816.25, E.M. Rs. 18 (Eighteen) Months,
Date of Opening: 03-01-2023 at 15-00 hrs.